SCHEDULE

Delay Analysis, Causes Of Delay & Corrective Measures
PERIODS & DATES:

START DATE 01 APR 09

PROJECT PERIOD 456 DAYS

FINISH DATE 30 JUN 10

FINISH DATE AS PER CPM UPDATE ON 13AUG 09 28 JUL 10
EXPECTED DELAY 28 DAYS
Delay Analysis
THE ITEMS LEAD TO DELAY:
Pehs0315 Sub. Of Ground Roof Structure Sh Dwg. & Details
Pems05121 Sub. Of Metal Roof Cladding Material & Accisso.
Pems05701 Sub. Of Tempered Glass Canopies Materials
Pems08015 Sub. Of Curtain Wall & Accessories
Pep14400 Proc. Of Conveying Materials

Corrective Measures
* During Next Week We Will Finalize All Ground Roof Slab Structure SH DWG
* After Getting Approval For Metal Work Sub Contractor We Will Start Immediately Submit The Metal Roof Cladding Materials
* After Getting Approval For Metal Work Sub Contractor We Will Start Immediately Submit The Tempered Glass Canopies Materials
* During Next 2 Weeks We Will Submit The Curtain Wall Materials & Accessories
* During Next 2 Weeks We Will Finalize the submittals for conveying materials
** RECOVERY ACTION FOR ((CCS))

· These relationship lags have been changed by revision.
--------------- ------------------------------------------------
PCBZ103355 CAST RC FOR BASEMENT ROOF SLAB-LEV. (+0.20)
PCNZ103345 SHUTTER FOR GROUND ROOF SLAB FS 10 8

PEHS0315 SUB. OF GROUND ROOF STRUCTURE SH DWG. & DETAILS
PEHA0315 APP. OF GROUND ROOF STRUCTURE SH DWG FF 14 8

PEOA05120 APP. OF METAL WORK SUB CONT.'S
PEMS05121 SUB. OF METAL ROOF CLADDING MATERIAL FS 21 0

PEMA05701 APP. OF TEMPERED GLASS CANOPIES MATERIALS
PEP05703 PROC. OF CANOPIES MATERIALS FS 30 28

PEMA08015 APP. OF CURTAIN WALL & ACCESSORIES
PEP08015 PROC. OF CURTAIN WALL & ACCESSORIES FS 45 35

PEMA15431 APP. OF RAIN WATER SYS SPECIALITIES MATERIALS
PEP154315 PROC. OF RAIN WATER SYS SPECIALITIE FS 14 10

· These original durations have been changed by revision.
---------- ------------------------------------------------ ------ --
PEP057025 PROC. OF METAL LOUVERS MATERIALS 75 70 -5
PEP14400 PROC. OF CONVEYING MATERIALS 100 95 -5